GENERAL INFORMATION
Tenative Start Date | September 6, 2022 |
Tentative Completion Date | September 23, 2022 |
Bid Opening | June 23, 2022 |
Project Manager | John Scott Mulford |
Contractor | Midwest Brick Paving |
Award Contract Amount | $100,000 |
Funding Sources | Capital Outlay Funds |
Project Information
This Project Includes: Removing and replacing brick pavers between the sidewalk and curb on Milwaukee Ave.
Project Limits: Just north of Dundee Rd to Strong Ave
Update:
9-7-22: Contractor started project on the east side.
9-14-22: Contractor complete the east side of Milwaukee Ave and is switching to the west side.
9-19-22: Project has been completed.