This Project Includes: removal of existing asphalt bike path and replacement of Hot-Mix Asphalt pavement.
Project Limits:
South Path:
Geneva Drive to the park district park.
North Path:
Geneva Drive to the bike path cul-de-sac.
Updates:
5-5-23: Accu-Paving began removal of the existing asphalt bike paths.