2017 Street Improvement Program

General Information

Tentative Start Date: May 30, 2017
Tentative Completion Date: August 14, 2017
Bid Opening: April 12, 2017
Project Manager: Jon Tack
Contractor: Peter Baker & Co.
Awarded Contract Amount: $779,720.52
Funding Sources: Motor Fuel Tax Fund and Capital Projects Fund

Project Information

 


This Project Includes:  Annual Village-wide Street Improvement Program provides for the resurfacing or, when necessary, the reconstruction of existing pavements according to a 5-year plan that is reevaluated and adjusted on an annual basis.  Streets are selected for improvement based on existing conditions and scheduling of cost effective rehabilitation strategies.

Project Limits: Meadowbrook West Subdivision, E. Jeffery Avenue, Marvin Place, Capitol Drive, Suncheon Drive, Gangnam Drive. 

Project Schedule:
TBD
  1. Jon Tack

    Village Engineer
    Phone: 847-499-9059

Communications


Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area.  Click here to sign up.

Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.

Project Updates



6/13/17
Curbs, sidewalk, and other concrete work continues in Meadowbrook East and West.

5/30/17

Curbs, sidewalk, and other concrete work will start on May 30th, at 7:30 am. The contractor will remove the designated areas of deteriorated curb on one side of the street at a time, as to lessen the need for on street parking while these affected residents are out of their driveways for the next 4-7 days.  

During construction, street parking will be allowed per posted signs. 

5/16/17
Curbs, sidewalk, and other concrete work is scheduled to start on June 1st. Temporary driveway access interruptions may be experienced, however, prior notifications will be made.

During construction, street parking will be allowed per posted signs.