2020 Eastchester Storm Sewer Improvements
General Information
Tentative Start Date: | May 2020 |
Tentative Completion Date: | September 2020 |
Bid Opening: | April 15, 2020 |
Project Manager: | Jon Tack |
Contractor: | Copenhaver Construction, Inc. |
Awarded Contract Amount: | $764,665.00 |
Funding Sources: | Storm Water Fund |
Project Information
This Project Includes: Storm sewer improvements that intend to redirect existing storm sewer flow from the Dunhurst neighborhood to Echo Lake.
Project Limits: Eastchester SubdivisionRelated Documents
Communications
Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area. Click here to sign up.
Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.
Project Updates
5.29.2020 - The contractor built the cofferdam and installed the outfall at the Echo Lake. Storm sewer installation is ongoing near the lake. Storm sewer work within the Eastchester Subdivision is tentatively scheduled to begin in 3-4 week, weather permitting.
6.02.2020 - On Friday, June 05, 2020, from 9:00 A.M to 3:00 P.M., weather permitting, Copenhaver Construction, Inc. will be performing necessary maintenance work on the water distribution system. Temporary interruption of your water service will be required. The crews will minimize the interruption to the extent possible.
A Notice of Water Service Interruption will be hand delivered to the affected residents.
6.04.2020 - On Friday, June 05, 2020, from 9:00 A.M to 3:00 P.M., weather permitting, Copenhaver Construction, Inc. will be performing necessary work on the water distribution system at Hastings Road and Garth Road.During this work, there will be no access to Hastings Court. If you need access to your vehicle during this time, please park on Garth Road or Hastings Road prior to 9:00 A.M.
6.5.2020 - Storm sewer installation is ongoing.
6.12.2020 - Storm sewer pipe installation is ongoing along the school property towards Hastings Road.
6.18.2020 - Storm sewer pipe installation is ongoing on Hastings Road.
6.26.2020 - Storm sewer installation on Hastings Road is ongoing.
7.02.2020 - Construction activities to resume after the holiday weekend. Street parking will be open during the weekend but no street parking will resume next week.
7.10.2020 - Storm installation on Hasting towards Garth to be complete in the next two week with curb and road work to follow.
7.17.2020 - Storm sewer structure and main pipe installation on Hasting Lane and Garth to be completed next week, followed by installation of lateral connection pipes and grates to the new storm sewer.
7.24.2020 - Underground work has been completed. Concrete work is scheduled for next week, weather permitting.
7.31.2020 - All concrete work completed. Grinding/Milling of existing asphalt will take place on Thursday of next week. Paving of the utility trenches will take place Friday of next week. Paving of the entire roadway will take place Monday of the following week.
8.7.2020 - Project is substantially complete. Landscape restorations and punch listed items remain.
8.21.2020 - Landscaping has been completed. Trees are scheduled to be planted next week.