London Pedestrian Bridge Maintenance Project

General Information

Tentative Start Date:July 11, 2022
Tentative Completion Date:August 12, 2022
Bid Opening:May 26, 2022
Project Manager:Kevin Pelli
Contractor:Builders Concrete
Awarded Contract Amount:$57,915
Funding Sources:Capital Outlay Fund


Project Information

 

 

This Project Includes: Patching concrete steps on leading to pedestrian bridge

Project Limits: London Pedestrian Bridge over Dundee Rd at London Middle School

Project Updates:

7-13-22: LP removed on north side steps.

7-20-22: 95% of the repairs have been made on the stairs

8-1-22 : Project complete