2023 MFT Program
General Information
Tentative Start Date | May 17, 2023 |
Tentative Completion Date | August, 25, 2023 |
Bid Opening | March 23,2023 |
Project Manager | Kevin Pelli |
Contractor | Builders Paving, LLC |
Awarded Contract Amount | 1,678,000.00 |
Funding Sources | MFT, TIF and Storm Sewer Funds |
Project Information
Roads to be resurfaced: 3rd Street, 2nd Street, 1st Street, Mayer Ave, E.Norman Ln, Fletcher Dr, Sarah Ct, Anthony Rd, Robert Ave, Thelma Ct, Albert Ter, Blaze Tr, Peace Dr (Blaze to Rose), Crimson Dr (S. of Twilight to Blaze) and Weeping Willow Dr (Honeysuckle to Willowbrook).
* Twilight Lane and Maureen Drive are not being resurfaced this year.
This Project Includes: The work consists of HMA surface removal, Class D patching, utility structure adjustment, drainage structure removal and replacement, combination concrete curb and gutter removal and replacement, sidewalk removal and replacement, ADA ramp replacement, HMA surface course placement, landscape restoration, and all incidental and collateral work work necessary to complete the project.
Project Location:
Updates:
5-16-23: Saw cutting on this year's 2023 MFT project did commence today as expected.
5-17-23: All curb marked for removal and replacement on the NPTSOS on Weeping Willow, Peace, Blaze and Crimson was removed.
5-18-23: All of the removed curb on Weeping Willow, Peace, Blaze and Crimson was framed for concrete pouring.
5-30-23: Contractor continuing to remove and replace curb and sidewalk.
6-7-23: Contractor continuing to remove and replace curb and sidewalk on 1st, 2nd and 3rd Streets.
6-9-23: Temporary road closure between 179 & 186 E Norman Lane for storm sewer installation.
6-19-23: The Contractor completed the concrete removal and replacement portion of this project. Milling and placing of new Hot-Mix-Asphalt is scheduled for after the July 4th Holiday.
6-28-23: Landscaping Contractor is working on restoration of the entire project.
7-14-23: Builders Asphalt, did complete the asphalt grinding on the following streets today, Robert, Anthony, Mayer, 3rd streets and 2nd St.
7-17-23: Today, Builders Asphalt, had their fine tuning / trimming team on Weeping Willow this morning and on East Norman Lane this afternoon. There was also a sweeper onsite in both locations, all day. Both streets are deemed ready for asphalt placement. Tomorrow, starting at 9:00am, Builders Asphalt will be applying the tack coat (oil) on the following streets, Weeping Willow, E Norman, Albert, W Norman, Fletcher and Sarah Ct. Tomorrow, Builder will be placing surface asphalt on Weeping Willow only. This asphalt placement will begin at approximately 12:00pm.
7-20-23: Builders Asphalt completed placing 1,188 tons of N50 surface asphalt on the following streets, Fletcher, Thelma, Robert and Anthony Rd.
8-1-23 : Builders Asphalt, has completed the paving of the final four streets on this year's 2023 MFT Street Resurfacing Project. 900 tons of N50 surface asphalt was placed on 1st St, 2nd St, north and south 3rd St. and Mayer Avenue, between 2nd St and Milwaukee Avenue.
8-16-23: Builders Asphalt asphalt driveway repairs.
8-17-23: Builders Asphalt completed the asphalt driveway patching today.
8-25-23: Striping contractor completed striping today on East Anthony. Punch list items remaining.
10-20-23: Punch list items complete. Project complete.