Chaddick Drive Resurfacing

General Information

Tentative Start Date: May 3, 2023
Tentative Completion Date:June 14, 2023
Bid Opening:March 17,2023 
Project Manager:Kevin Pelli
Contractor:Builders Paving, LLC
Awarded Contract Amount:$392,000.00
Funding Sources:Rebuild Illinois Funds


Project Information

This Project Includes: Removal and replacement of concrete curbs and sidewalks, milling of the existing asphalt and resurfacing with new Hot-Mix Asphalt.

Chaddick

Project Limits: Marquardt Dr to Hintz Road 

Updates:  5-3-23: Concrete contractor began removal of the curbs and sidewalks to be replaced. 

5-5-23: Concrete contractor poured 72 CY of concrete curb on the east and west sides.

5-15-23: Concrete contractor poured  the other halves of driveway curbs that were not done last week. 6-19-23: Builders Asphalt did complete the grinding of 2 and a half inches of existing asphalt off of South Chaddick Drive. There was 102 semi loads of asphalt grinding transported to Builders Asphalt plant here in Wheeling, for future recycling. This came out to approximately 13,000 square yards or approximately 2,140 tons of asphalt grindings.

6-21-23: Builders Asphalt has completed, with the placement of 553 tons of polymeric leveling binder asphalt on all of S Chaddick today. 

6-22-23: This morning, H&H Electric, did install the new loop detector on the north end of S Chaddick. DeVinci Construction, adjusted a total of 9 storm sewer structures and 1 sanitary sewer structure. Once adjusted, they had batch plant concrete poured around them. They are now barricaded with flashers and will cure for the next 4 days.

6-27-23: Be advised that Builders Asphalt completed the placement, of the surface asphalt today, on S Chaddick, between Hintz Rd and Marquart Drive. A total of 1,446 tones of surface asphalt was placed. 72 semi-truck loads were picked up and delivered, from the Builder’s asphalt plant here in Wheeling. Tomorrow, DeMarr will be placing the yellow skip dashes down all of S Chaddick.

8-3-24: Builders Asphalt completed patch the 2 driveways at 945-995 S. Chaddick. This completes the project.