Northgate Parkway Resurfacing

General Information

Tentative Start Date:August 21, 2023
Tentative Completion Date:November 1, 2023
Bid Opening:June 16, 2023
Project Manager:Kevin Pelli
Contractor:Builders Paving, LLC
Awarded Contract Amount:$782,668.00
Funding Sources:STP and Rebuild Illinois Funds


Project Information

 

 

This Project Includes: Curb and sidewalk replacement, milling and placing new Hot Mix Asphalt.

Project Limits: Bridge South of Egidi Dr to Lake-Cook Road.

Northgate Parkway


Updates: 6-16-23: Bid opening took place. Builders Paving was the low bidder. IDOT is working on getting the contracts executed.
7-11-23: Contract Awarded to Builders Paving, LLC
7-26-23 Contract Executed   
8-8-23 : Pre-Construction Meeting was held. Contractor plans to start on August 21,2023.
8-25-23:  Project is now scheduled to start on 8-28-23.                                                                               9-6-23: Concrete Contractor is removing and forming C&G and sidewalk replacements today and tomorrow, Inlet adjustments are scheduled for tomorrow and then planning for concrete pour on Friday AM. 
10-2-23: Builders Paving completed milling the entire project.
10-3-23: Builders Paving is placing Hot Mix Asphalt Leveling Binder.
10-9-23: Builders Paving started placing the final surface course of asphalt.
10-10-23: Builders Paving completed the final surface course of asphalt. Pavement Marking  to follow soon.
10-28-23: Striping was completed.









8