- Home
- Government
- Departments
- Public Works
- Engineering and Capital Projects Division
- Capital Improvement Projects
- 2023 Paver Brick Maintenance
Tentative Start Date: | May 8, 2023 |
Tentative Completion Date: | June 1, 2023 |
Bid Opening: | June 3, 2022 |
Project Manager: | Kevin Pelli |
Contractor: | Midwest Brick Paving |
Awarded Contract Amount: | $ 220,999.25 |
Funding Sources: | Capital Improvement and TIF Funds |
This Project Includes: The removal and replacement of paver bricks between the curb and sidewalk along Milwaukee Ave.
Project Limits: North of Strong Ave and then Dundee Road to the south on both sides of Milwaukee Ave.5-8-23: Midwest Brickpaving began removing and replacing paver bricks on the east side of Milwaukee Ave north of Strong Ave.
5-12-23: Midwest Brick Paving continued removing and replacing paver bricks on the east side of Milwaukee Ave. They have completed the east side and have started on the north end on west side of Milwaukee Ave.
5-18-23: Midwest Brickpaving has completed the removal and replacement of approximately 10,000 square feet of paver bricks on both the east and west sides of the street on northbound Milwaukee Avenue, between Dundee Rd and N Wolf Road.
Updates:
6-28-23: Corrective Asphalt Materials (CAM) started placing Reclamite, an asphalt rejuvenator on the streets around Strong Ave.
6-30-23: Corrective Asphalt Materials finished the area around Strong and then did the industrial area at Allis, Noel, Gilman and Willis. 11th and 12th , south of Strong Ave were skipped due to permitted parking for driveways replacements at residences on these streets and could be done later in the season.