2016 Street Improvement Program
General Information
Tentative Start Date: | June 13, 2016 |
Tentative Completion Date: | August 2016 |
Bid Opening: | April 27, 2016 |
Project Manager: | Jon Tack |
Contractor: | Schroeder Asphalt,Services, Inc. |
Awarded Contract Amount: | $751,835.43 |
Funding Sources: | Motor Fuel Tax Fund and Capital Projects Fund |
Project Information
This Project Includes: Annual Village-wide Street Improvement Program provides for the resurfacing or, when necessary, the reconstruction of existing pavements according to a 5-year plan that is reevaluated and adjusted on an annual basis. Streets are selected for improvement based on existing conditions and scheduling of cost effective rehabilitation strategies.
Project Limits: Jackson Drive, Eastchester, Mercantile Ct., Harvester Ct. Exchange Ct., Denniston Ct. and Seton Ct.Project Schedule: June to August
Related Documents
Communications
Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area. Click here to sign up.
Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.
Project Updates
8.30.2016
Reconstruction of Exchange Court is scheduled to being on August 31, 2016 at approximately 4:00 am. On Thursday, September 1st, driveway aprons saw cutting and prepping is scheduled to commence on Jackson Drive. The asphalt surface course pavement will be installed on the driveways and Jackson Drive on Friday, September 2nd, weather permitting.8.18.2016
Pavement removal and asphalt paving in Eastchester Subdivision, Mercantile Ct., Harvester Ct., Denniston Ct. and Seton Ct. is complete. Reconstruction of Exchange Ct. is scheduled to commence on August 26th. The asphalt surface course pavement on Jackson Dr. will be installed at a later date.
6.13.2016
The construction schedule for project is as follows, weather permitting:
June 13 to June 28 – Concrete, sewer, and landscape restorations for the entire project.
July 9 to July 16 – Pavement removal and stone base on Exchange Court.
July 11 to July 18 – Pavement removal and asphalt paving for the entire project.
All streets in construction zone will be open but you will encounter delays as we load and unload materials. All driveways will be open during construction except for when we are milling, installing asphalt in the driveway or when asphalt is being placed in the road near the driveway.
Schroeder Asphalt will notify residents / business owners and make arrangements to ensure you have use of your vehicles during this time. Thank you for your patience and understanding during construction.
July 9 to July 16 – Pavement removal and stone base on Exchange Court.
July 11 to July 18 – Pavement removal and asphalt paving for the entire project.
All streets in construction zone will be open but you will encounter delays as we load and unload materials. All driveways will be open during construction except for when we are milling, installing asphalt in the driveway or when asphalt is being placed in the road near the driveway.
Schroeder Asphalt will notify residents / business owners and make arrangements to ensure you have use of your vehicles during this time. Thank you for your patience and understanding during construction.