2017 Watermain Replacement & Roadway Improvement Program
General Information
Tentative Start Date: | 05/15/2017 |
Tentative Completion Date: | Completed |
Bid Opening: | 04/05/2017 |
Project Manager: | Lana Rudnik |
Contractor: | Trine Construction Corp. |
Awarded Contract Amount: | $2,070,995.00 |
Funding Sources: | Water & Sewer Fund and Capital Projects Fund |
Project Information
This Project Includes: 5,580 linear feet of 8" watermain, valves, vaults, hydrants and other associated work. New sidewalks and fiber lines will be installed along each roadway, and driveway aprons will be replaced as needed. All roadways will be either be reconstructed or resurfaced.
Project Limits: Glenn Avenue, Carpenter Avenue, Shepard Avenue.Project Schedule: TBD
-
Kevin Pelli
Engineering CoordinatorPhone: 847-279-6912
Related Documents
Communications
Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area. Click here to sign up.
Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.
Project Updates
Watemain, sidewalks and road work are complete. Fiber optic cable installation is ongoing.
8.25.17
Beginning at 9:00 am, on the morning of Thursday, August 31st 2017, our watermain contractor, (Trine Construction) will be closing Glenn Avenue at Hintz Road. This road closure will commence on the 31st of August and the road is anticipated to be reopened to all traffic on the morning of September 6th 2017. The traffic will be redirected to Chaddick Drive with local traffic only between Shepard Avenue and the road closure at Hintz Road (please see attached map for more details).
This road closure is needed for the extensive concrete restoration work that needs to take place at this intersection, it is part of our 2017 Watermain Replacement project. Due to the 7 days of curing time that it will take to ensure that the concrete has cured sufficiently and that the new concrete can withstand the exorbitant amount of weight and traffic that the road endures, it is critical that this intersection remains closed for the 7 days.
6.23.17As part of the 2017 Watermain Replacement Project, the contractor will be working at the intersection of Glenn Ave and Hintz Road on June 26th and 27th. The work will require a road closure on Glenn Avenue at the intersection of Hintz Road. The traffic will be redirected to Chaddick Drive with local traffic only between Shepard Avenue and the road closure at Hintz Road. Road closure and detour signs will be placed per IDOT standard.
5.30.17
New watermain on Shepard Avenue is in service and the fire hydrants are operational. New watermain on Carpenter is installed and the pressure test is scheduled. Work continues on Glenn Avenue.
5.30.17
Work continues on Shepard Avenue and Carpenter Avenue and Glenn Avenue.
5.11.17
Watermain construction work is scheduled to commence on May 15th on Shepard Avenue. On Tuesday, May 16th, a second construction crew will begin work at the end of Carpenter Avenue.