Diversionary Channel Bridge and Roadway

General Information

Bid Opening: August 13, 2018
Project Manager: Jon Tack
Contractor: Lorig Construction Co.
Awarded Contract Amount: $1,974,546.00
Funding Sources: TIF Funds

Project Information

 

This Project Includes:  A vehicular bridge and roadway access to and from a bridge span to be located across the Wheeling Diversionary Channel.  The roadway access design east of the bridge should originate from Milwaukee Avenue and use the existing easement through the RAM Restaurant property.  The roadway access design west of the bridge should extend 100 linear feet beyond the bridge.

Project Limits: Wolf Court 


Related Documents

Communications


Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area.  Click here to sign up.

Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.

Project Updates



Live webcam on Diversionary Channel Bridge Project

2.14.19  
The contractor has completed substantial earth work, particularly on the west side of the Diversionary Channel, and done additional excavation on the east side of the Channel; the protective wall for the AT&T utilities has not yet been installed.  Contractor mobilization had been delayed by recent weather events, and a revised construction schedule is expected this week.